Marine Facilities

Berthing Facilities (5 Berths: Iron Ore 1; Coal 1; Multipurpose 3)

Depth in harbor 19.5m below CD

Mechanized Coal and Iron Ore discharge system for vessel size upto 200,000 DWT

Mechanized Wagon Loading and Wagon Tippling System

New generation Mobile Harbor Cranes for other bulk and break bulk cargoes

Coal stackyard and Iron ore stackyard with storage capacity of approximately
    1 MMT each

Covered transit storage for bulk and break cargoes

Extensive ancillary facilities and state-of-the-art utilities / services

Flexibility for future expansion of cargo handling facilities as per demand

Round the clock Cargo handling and Marine operations

Environmental friendly operation

  Berths   Size   Alongside Depth
1
  Coal Cargo   320 x 25 m   19.50 m below CD
2
  Iron Ore Cargo   340 x 25 m   19.50 m below CD
3
  Other Dry Cargo   275 x 31 m   15.50 m below CD
4
  Multipurpose Cargo   281 x 31 m   15.50 m below CD
5
  General Cargo   242 x 28 m   14.00 m below CD
Berth Configuration in Phase 1


Cargo Handling Facilities

New generation mechanized cargo handling system has being installed at Gangavaram Port for faster and efficient handling and evacuation of cargo with minimum handling loss. Cargo handling equipment installed in Phase-I development include, Ship Loader for bulk exports, Ship Unloaders for bulk imports, Mobile Harbour Cranes for bulk/break bulk cargo, associated conveyer system for transportation to and from stackyard, Stackers & Reclaimers for stackyard operations and Wagon loader & Wagon tipplers for handling Railway rakes.


Click for Image of Phase-1 Development Plan