| Project
Timeframes |
Status |
| Concession
Agreement |
Signed |
| All
Statutory clearances for Project execution |
Obtained |
| Project
Appraisal and Financial Closure |
Completed |
| Commencement
of Construction |
December
2005 |
| Iron
Ore Berth Construction and Fittings |
Completed |
| Coal
Berth Construction and Fittings |
Completed |
| South
and North Breakwaters |
Completed |
| Other
General Cargo Berths |
Completed
|
| Delivery & Installation
of Coal Unloaders,Iron Ore Loader and Mobile Harbor Cranes |
Completed
|
| Completion
of Stackyard |
August 2008
|
| Phased Commissioning
of the Port |
Commissioned (August 2008) |
|
|
|
Project Milestones |
| Gangavaram Port
Awarded "Infrastructure Deal of the Year" -
2005 for Asia - Pacific Region" |
| Gangavaram Port handles four
vessels at the Port with Project equipment between
November 2007 and March 2008 |
| Phased commercial commencement
of the Port by handling first vessel on 3 August 2008 and second vessel on 4 August 2008 |